Standard abatement (NRS 360.750)
Agru America
Promised and audited
| Measure | Promised (contract) | Audited |
|---|---|---|
| Jobs | 17 | Not published |
| Average hourly wage | $29.00/hr | Not published |
| Capital investment | $20,872,500 | Not published |
| Tax revenue generated | Not stated | Not tracked by GOED |
| Economic activity | Not stated | Not tracked by GOED |
The audit table lists the projection as 17 jobs, $28.62/hr and $356,860 (p. 68).
Taxes abated (contracted)
- Total abated, as listed
- $1,383,440
- Statute
- NRS 360.750
Source: GOED, Abatement Biennial Report FY22–FY24 (report to the Legislature under NRS 231.0685), p. 42 (PDF p. 48); audit table p. 68. Amounts are what the contract allows over its term, not abatements taken to date; GOED does not publish amounts taken.
Compliance audits
Data Center and Aviation abatements are audited at the 2, 5, 8, and 10-year mark (standard abatements at 2 and 5 years), by the Nevada Department of Taxation. Contract effective Jul 22, 2024.
- 2-year audit Due; no result publishedDue Jul 22, 2026
- 5-year audit Not in the reportDue Jul 22, 2019
Proposal, not adopted: each audit result published within 12 months of its due date.
Data-quality flags
No row-level flags. Report-level flags that apply to every row are on the flags page.