Real public dataClark County · May 2018 (FY2018) · withdrew after approval
Withdrew after approval

Promised and audited

Promised against audited figures
MeasurePromised (contract)Audited
Jobs50Not published
Average hourly wage$37.00/hrNot published
Capital investment$1,082,500Not published
Tax revenue generatedNot statedNot tracked by GOED
Economic activityNot statedNot tracked by GOED

Taxes abated (contracted)

Total abated, as listed
$177,195
Statute
NRS 360.750

Source: GOED, Abatement Biennial Report FY22–FY24 (report to the Legislature under NRS 231.0685), p. 28 (PDF p. 34); audit table p. 62. Amounts are what the contract allows over its term, not abatements taken to date; GOED does not publish amounts taken.

Compliance audits

Data Center and Aviation abatements are audited at the 2, 5, 8, and 10-year mark (standard abatements at 2 and 5 years), by the Nevada Department of Taxation.

  1. 2-year audit No audit (withdrew)–
  2. 5-year audit No audit (withdrew)–

Proposal, not adopted: each audit result published within 12 months of its due date.

Data-quality flags

No row-level flags. Report-level flags that apply to every row are on the flags page.