Prototype
Real public dataStorey County · Announced Feb 5, 2026
Audit dates not published

Promised and audited

Promised against audited figures
MeasurePromised (contract)Audited
Jobs (within five years)14Not published
Average hourly wage$54.29/hrNot published
Capital investment$300,000,000Not published
Tax revenue generated$45,743,902 projectedNot tracked by GOED
Economic activityNot statedNot tracked by GOED

Taxes abated (contracted)

Total abated, as listed
$23,350,806
Statute
NRS 360.754 (program as approved; see release)

Source: GOED newsroom release, 2026-02-05. Amounts are what the contract allows over its term, not abatements taken to date; GOED does not publish amounts taken.

From GOED's announcement. The release does not cite the statute; the next biennial report will list the contract.

Compliance audits

Data Center and Aviation abatements are audited at the 2, 5, 8, and 10-year mark (standard abatements at 2 and 5 years), by the Nevada Department of Taxation. The contract start date is not published yet, so the audit dates are not known.

  1. 2-year audit Start date not published–
  2. 5-year audit Start date not published–
  3. 8-year audit Start date not published–
  4. 10-year audit Start date not published–

Proposal, not adopted: each audit result published within 12 months of its due date.

Data-quality flags

Identical figuresOpen

Same terms as an earlier approval

GOED's releases give SV RNO Property Owner 1, LLC (Feb 2026) and PR TX 1, LLC (Nov 2025) the same jobs (14), wage ($54.29), capital ($300,000,000) and abatement ($23,350,806). The figures may be correct; the board packets are the record to confirm.

Source: GOED newsroom releases, Nov 10, 2025 and Feb 5, 2026