Prototype

Data-center abatement (NRS 360.754)

Via West (now Flexential Corp.)

Real public dataClark County · May 2016 (FY2016)
1 of 4 due audits reported

Promised and audited

Promised against audited figures
MeasurePromised (contract)Audited
Jobs100
Average hourly wage$31.90/hrNot published
Capital investment$49,278,038$4,210,768
Tax revenue generatedNot statedNot tracked by GOED
Economic activityNot statedNot tracked by GOED

The audit table lists the projection as 10 jobs, $31.90/hr and $49,278 (p. 60).

Taxes abated (contracted)

Total abated, as listed
$3,785,763
Sales and use tax
$2,799,193
Personal property tax
$986,570
Annual wages, as listed
$663,520
Jobs × hourly wage × 2,080 hours
$663,520
Statute
NRS 360.754

Source: GOED, Abatement Biennial Report FY22–FY24 (report to the Legislature under NRS 231.0685), p. 48 (PDF p. 54); audit table p. 60. Amounts are what the contract allows over its term, not abatements taken to date; GOED does not publish amounts taken.

Compliance audits

Data Center and Aviation abatements are audited at the 2, 5, 8, and 10-year mark (standard abatements at 2 and 5 years), by the Nevada Department of Taxation. Contract effective May 19, 2016.

  1. 2-year audit CompliantDue Apr 1, 2018
  2. 5-year audit Pending in the reportDue Apr 1, 2021
  3. 8-year audit Not in the reportDue May 19, 2024
  4. 10-year audit Due; no result publishedDue May 19, 2026

Proposal, not adopted: each audit result published within 12 months of its due date.

Data-quality flags

Unexplained differenceOpen

Audit shows 0 jobs against 10 contracted; 2-year audit marked compliant

The audit findings list 0 jobs and $4,210,768 in capital against 10 contracted jobs. The 2-year audit (Apr 1, 2018) is marked compliant; the 5-year audit (Apr 1, 2021) is still marked pending in the January 2025 report. The report does not explain the difference.

Source: GOED Abatement Biennial Report FY22–FY24, p. 60 (PDF p. 66)

Sources differOpen

Capital investment differs between tables

The data-center table lists $49,278,038 in capital; the audit table lists $49,278 as the projection.

Source: GOED Abatement Biennial Report FY22–FY24, p. 60 (PDF p. 66)